MIPP120

SmartWorks Project Planner


Project Summary - MIPP120

Task List

ID Name Status Duration Start End Dependancy Owner Resources Cost
1 MIPP120 (MIPP120)  90% Complete  58.0 d  15/04/05  11/06/05        0.000 
2  Refurbish Collimator  Complete  46.0 d  15/04/05  30/05/05        0.000 
3   Fill up extra holes  Complete  8.0 d  19/04/05  26/04/05        0.000 
4   Add in 1mm slit  Complete  8.0 d  19/04/05  26/04/05        0.000 
5   Control collimator  Complete  46.0 d  15/04/05  30/05/05        0.000 
6  Develop 120 GeV tune  Complete  38.0 d  18/04/05  25/05/05        0.000 
7  Develop Interlocks  90% Complete  37.0 d  19/04/05  25/05/05        0.000 
8  Develop 3 Way splits  Complete  12.0 d  18/04/05  29/04/05        0.000 
9  Installation of beamline elements  Complete  2.0 d  06/06/05  07/06/05        0.000 
10   Install Pinhole collimator  Complete  2.0 d  06/06/05  07/06/05        0.000 
11   Install shielding  Complete  2.0 d  06/06/05  07/06/05        0.000 
12   Remove Primary target  Complete  0.0 d  06/06/05  06/06/05        0.000 
13  Calculate Ground water activation  Complete  9.0 d  19/04/05  27/04/05        0.000 
14  Write Safety Documentation  Complete  37.0 d  19/04/05  25/05/05        0.000 
15  Safety Walk Through  New Task  1.0 d  09/06/05  09/06/05  22 FS      0.000 
16  Get Safety Approval  New Task  1.0 d  10/06/05  10/06/05  15 FS      0.000 
17  Build Target assembly  Complete  15.0 d  11/05/05  25/05/05        0.000 
18   Fabricate Stand  Complete  10.0 d  11/05/05  20/05/05        0.000 
19   Mount target on stand  Complete  1.0 d  24/05/05  24/05/05        0.000 
20   Mount UVA assembly  Complete  1.0 d  25/05/05  25/05/05        0.000 
21   Mount Indiana trigger  Complete  1.0 d  25/05/05  25/05/05        0.000 
22  Install target in MC7  Complete  5.0 d  04/06/05  08/06/05        0.000 
23  Install new SWICs in MC7  Complete  2.0 d  06/06/05  07/06/05        0.000 
24  Surveying  Complete  18.0 d  25/05/05  11/06/05        0.000 
25   Survey NUMI target in PAB  Complete  1.0 d  25/05/05  25/05/05        0.000 
26   Survey Indiana trigger in PAB  Complete  1.0 d  26/05/05  26/05/05        0.000 
27   Survey UVA assembly in PAB  Complete  1.0 d  27/05/05  27/05/05        0.000 
28   Survey Pinhole in M02 before shielding  Complete  1.0 d  08/06/05  08/06/05  10 FS      0.000 
29   Survey Pinhole after shielding  Complete  1.0 d  08/06/05  08/06/05  11 FS      0.000 
30   Survey SWICs in MC7  Complete  1.0 d  09/06/05  09/06/05  29 FS      0.000 
31   Survey NUMI target assembly in MC7  Complete  2.0 d  10/06/05  11/06/05  30 FS      0.000 

User - admin

10 June, 2005