MIPP120 | SmartWorks Project Planner |
| ID | Name | Status | Duration | Start | End | Dependancy | Owner | Resources | Cost |
| 1 | MIPP120 (MIPP120) | 90% Complete | 58.0 d | 15/04/05 | 11/06/05 | 0.000 | |||
| 2 | Refurbish Collimator | Complete | 46.0 d | 15/04/05 | 30/05/05 | 0.000 | |||
| 3 | Fill up extra holes | Complete | 8.0 d | 19/04/05 | 26/04/05 | 0.000 | |||
| 4 | Add in 1mm slit | Complete | 8.0 d | 19/04/05 | 26/04/05 | 0.000 | |||
| 5 | Control collimator | Complete | 46.0 d | 15/04/05 | 30/05/05 | 0.000 | |||
| 6 | Develop 120 GeV tune | Complete | 38.0 d | 18/04/05 | 25/05/05 | 0.000 | |||
| 7 | Develop Interlocks | 90% Complete | 37.0 d | 19/04/05 | 25/05/05 | 0.000 | |||
| 8 | Develop 3 Way splits | Complete | 12.0 d | 18/04/05 | 29/04/05 | 0.000 | |||
| 9 | Installation of beamline elements | Complete | 2.0 d | 06/06/05 | 07/06/05 | 0.000 | |||
| 10 | Install Pinhole collimator | Complete | 2.0 d | 06/06/05 | 07/06/05 | 0.000 | |||
| 11 | Install shielding | Complete | 2.0 d | 06/06/05 | 07/06/05 | 0.000 | |||
| 12 | Remove Primary target | Complete | 0.0 d | 06/06/05 | 06/06/05 | 0.000 | |||
| 13 | Calculate Ground water activation | Complete | 9.0 d | 19/04/05 | 27/04/05 | 0.000 | |||
| 14 | Write Safety Documentation | Complete | 37.0 d | 19/04/05 | 25/05/05 | 0.000 | |||
| 15 | Safety Walk Through | New Task | 1.0 d | 09/06/05 | 09/06/05 | 22 FS | 0.000 | ||
| 16 | Get Safety Approval | New Task | 1.0 d | 10/06/05 | 10/06/05 | 15 FS | 0.000 | ||
| 17 | Build Target assembly | Complete | 15.0 d | 11/05/05 | 25/05/05 | 0.000 | |||
| 18 | Fabricate Stand | Complete | 10.0 d | 11/05/05 | 20/05/05 | 0.000 | |||
| 19 | Mount target on stand | Complete | 1.0 d | 24/05/05 | 24/05/05 | 0.000 | |||
| 20 | Mount UVA assembly | Complete | 1.0 d | 25/05/05 | 25/05/05 | 0.000 | |||
| 21 | Mount Indiana trigger | Complete | 1.0 d | 25/05/05 | 25/05/05 | 0.000 | |||
| 22 | Install target in MC7 | Complete | 5.0 d | 04/06/05 | 08/06/05 | 0.000 | |||
| 23 | Install new SWICs in MC7 | Complete | 2.0 d | 06/06/05 | 07/06/05 | 0.000 | |||
| 24 | Surveying | Complete | 18.0 d | 25/05/05 | 11/06/05 | 0.000 | |||
| 25 | Survey NUMI target in PAB | Complete | 1.0 d | 25/05/05 | 25/05/05 | 0.000 | |||
| 26 | Survey Indiana trigger in PAB | Complete | 1.0 d | 26/05/05 | 26/05/05 | 0.000 | |||
| 27 | Survey UVA assembly in PAB | Complete | 1.0 d | 27/05/05 | 27/05/05 | 0.000 | |||
| 28 | Survey Pinhole in M02 before shielding | Complete | 1.0 d | 08/06/05 | 08/06/05 | 10 FS | 0.000 | ||
| 29 | Survey Pinhole after shielding | Complete | 1.0 d | 08/06/05 | 08/06/05 | 11 FS | 0.000 | ||
| 30 | Survey SWICs in MC7 | Complete | 1.0 d | 09/06/05 | 09/06/05 | 29 FS | 0.000 | ||
| 31 | Survey NUMI target assembly in MC7 | Complete | 2.0 d | 10/06/05 | 11/06/05 | 30 FS | 0.000 |
User - admin | 10 June, 2005 |