Bob Wood's calculations regarding the shoring needed in Mbottom were accepted by FESS.
MC7 schedule:
September 5th &endash; begin steel fabricationSeptember 17th &endash; begin concrete slab installation
September 10th &endash; start lowering steel into MB
Requisitions have been submitted for materials and labor to close roof & add overhead door in the section where the BM 109s were removed and for materials that will be needed to install a higher roof from the analysis magnets in DS MC7.
Raja has completed the momentum resolution studies and will forward the results to all collaborations members for their evaluation and input.
Before extraction studies can be schedules for a couple of shifts, quadrapoles must be installed in MI extraction line. A window to install the quads has opened because of an impromptu accelerator shutdown Monday &endash; Wednesday.
The next meeting will be Wednesday, September 12, Theory Room, WH3NE at 10:30AM.