Upon further inspection, the damaged coil has a spot where the copper is compressed 1/4" to 3/8". There does not appear to be turn to turn damage, however, the water path might be restricted from the compression. The coil will be taken to MAB where a flow test will be conducted.
All coils will be flushed with a hot water system. Additionally, a flow test will be conducted on each coil.
Procedural steps and drawings have been prepared for the magnet installation. Additionally, we are proceeding on the basis that the magnet will be located in MC7 using a rule only i.e. no official survey will be conducted prior to magnet installation.
US roof repair and OH door installation is re-scheduled to begin Monday, October 15. Also, installation of the 12" concrete slab is complete.
TPC - Terry Tope reports that he has completed a material list and a design so the existing gas rack can be modified. Modification to the rack will commence soon.
The drawings that show RICH support stand design are nearly complete.
Unfortunately, Thornton will not be making any more reports. We are sorry to hear of his passing Friday morning, October 12th.
The next meeting will be Wednesday, October 17, Theory Room, WH3NE at 10:30AM.
[ Meeting October 17 cancelled; next meeting October 24. - PDB]