The damaged coil has been moved to MAB where connections to prepare for a flow check are in process.
Coil flushing is in process. Flushing on one of four coils is completed.
Design and drawings of the support stand needed in MC7 are complete. Purchase of material for fabrication is on hold until new money is in place.
(Terry Tope) Gas system hookup is in process and expected to be completed by Friday the 26th. Safety approval to operate the system is expected the week of the 29th.
(Peter Barnes) DAQ software & cosmic trigger activities are progressing well.
HV testing is in progress. Some chambers need upgrade work before HV testing can take place. Probably 4 of the 6 chambers will be used in the experiment.
Craig Moore is the temporary contact for Beams. He will appoint a permanent person in due time.
Other than work on the TPC, per John Cooper, other systems will not receive Fermilab personnel effort until after the PAC meeting.
The next meeting will be Wednesday, October 29, Theory Room, WH3NE at 10:30AM.
[ Meeting October 29 cancelled; next meeting November 14. - PDB]