Leon Beverly, 11-20-01
Minutes of E907 meeting on Wednesday November 21, 2001
1. Magnet Installation
Issues regarding analysis magnet installation:
- Move Longo calorimeter to ME7 temporarily.
- Build plywood wall to isolate US MC7.
- Cover & weather proof cable pit DS MC7.
- Remove LCW headers, lights, tray from west wall.
- Move JGG steel pieces to vicinity of MC7.
- Cover JGG & Rosie steel pieces.
- Check to see if crane outrigger fit into side of MC7.
- Remove roof panels as needed.
- Engineer approved installation procedure.
- Lay down epoxy grout pad to level magnets.
- Schedule roof replacement in segments?
2. MOU
Development of the MOU is progressing.
3. Next Meeting
The next meeting will be Wednesday, November 28, Theory Room,
WH3NE at 10:30AM.