Peter will get clarification on what appears to be overlapping equipment per Raja's E907 positions document.
Jim Ellermierer will locate the JGG position and prepare for laying down a grout bed for both the JGG & Rosie.
Jim Kilmer will pursue the development of documents that describe the engineering procedure for the installation of both magnets.
Flushing of all four JGG coils has been completed.
Peter will jog Ed Hartouni to identify which E690 chamber will be designated as Chamber 1, 2, etc.
In preparation for E907 move in, clean out of what remains from E871 in the counting house PKs has started. A request has been made to get new carpet installed in the north PK.
Still awaiting new budget codes to begin FY02 work.
The next meeting will be Wednesday, January 16, Theory Room, WH3NE at 10:30AM.