Rosie concrete slab design is complete. Gary will make a drawing.
Jim Ellermeier will update draft copy of the installation procedure for the JGG. And produce a first draft of a Rosie installation procedure.
No work this week on support stand
Stand design complete, waiting for person to do drawing.
Ingrid &endash; please forward me your support stand (NCAL, other?) cost that you have with CC: Peter.
Due to thick rail plate needed under NCAL, the RICH height has to be adjusted down. Lowering of the RICH will be done using smaller diameter casters. Jim Kilmer will get drawings updated and seek an outside M&S cost quote. Also Jim will break down the in-house cost of $11k into materials (+16%) and labor (+31%).
I will get Carl Lindenmeyer to look at design for bracket to support pc cards on E690 chambers.
Jim will have an analysis done on Rosie's field, both US (TOF area) & DS (RICH area), to see the field level outside of the mirror plates.
OH door, west side of MC7 &endash; further discussion &endash; Jim Kilmer will investigate how easily, or not, chambers could go such a door, what door height is needed.
Livermore ICO has cleared the Governor's office in Cal., now to DOE Oakland and then to DOE Chicago.
Peter to ask systems people for alignment needs &endash; what type of alignment, how much time is involved, details of alignment needs.
The next meeting will be Wednesday, 13 March, Theory Room, WH3NE at 10:30AM.