E907 Installation Meeting Minutes

13 March 2002 Contents

  1. Magnets
  2. CKOV
  3. NCAL
  4. RICH
  5. Support Stands - Make or Buy
  6. Chambers & MC7 Access
  7. TOF & Fringe Fields
  8. Alignment
  9. Beam CKOV
  10. Purchase Orders
  11. Next Meeting


Leon Beverly, 3-14-02

Minutes of E907 meeting on Wednesday March 13, 2002

1. Magnets

A drawing showing the additional 12" high concrete slab to support Rosie is complete. Next I will get a quote for installation.

Jim Ellermeier updated the draft copy of the installation procedure for the JGG (see attached). Forward any further comments to Jim.

A first draft of a Rosie installation procedure will come March 27th.

2. CKOV

Support stand design is 30% complete. The expectation is to complete the design in 3 weeks.

3. NCAL

Stand design complete, still waiting for person to do drawing. Preliminary Direct M&S cost is $5.5K

4. RICH

Due to thick rail plate needed under NCAL, the RICH height had to be adjusted down. The RICH support stand drawing has been revised, but needs to be checked.

5. Support Stands - Make or Buy

Support stands for CKOV, RICH, & NCAL &endash; the current plan is to go outside the lab to fabricate these stands because it is less costly.

6. Chambers & MC7 Access

Scheme to get E690 chambers in and out of MC7 is not developed, but consensus of Hartouni, et al. go ahead with overhead door (14' ht X 12' wide) on west side of MC7.

7. TOF & Fringe Field

Fringe Field calculation done?

8. Alignment

In queue &endash; check floor points and mark beam line on floor and place 2 analysis magnets

9. Beam CKOV

Kilmer has some 10" iron pipe to use for beampipe. At some point the pieces of pipe will be moved into MC7 and welded together.

10. Purchase Orders

Placing purchase orders: Per Peter's request, Jim Kilmer has found out that Fermilab can spec jobs and Livermore can place a purchase order to execute the jobs. Livermore funds have not arrived at Fermilab. However, we can expedite jobs by Livermore placing an order now. Potential candidate jobs are:, support stands, MC7 roof material and installation, concrete slab for Rosie.

11. Next Meeting

The next meeting will be Wednesday, 20 March, Theory Room, WH3NE at 10:30AM.


PDB, 3/18/02