E907 Installation Conference Call Minutes

2 May 2002

Phone Number

Access Code:

775-785-1944

536495

Contents

Agenda

Progress Updates and Issues

  1. Upstream Beamline
    1. BEAM - Beamline
    2. UBL - Upstream Beamline Detectors
  2. Targets
    1. TGTW - Target Wheel
    2. CTGT - Cryo Targets
    3. NTGT - NuMI (MINOS) Target
  3. TPC - Time Projection Chamber
  4. Magnets
    1. JGG - Jolly Green Giant
    2. Rosy
  5. CKOV - Cerenkov
  6. DC - Chambers
  7. TOF - Time of Flight
  8. RICH - Ring Imaging Cerenkov
  9. NCAL - Calorimeter
  10. DAQ - Data Acquisition
  11. MC - Monte Carlo
  12. Installation
    1. Alignment
  13. MC7 - Enclosure and Counting House
  14. Meetings
  15. Project Management

Next Call


Agenda

Time (CST)

Dur (min)

Lead

Topic

3:00

5'

call setup

Chuck Brown

BEAMS

Mike Heffner

Beam CKOV

Peter Barnes

TPC

Jim Ellermeier

Magnets

Ingrid Fang
Gary Johnson

CKOV Stand design and drawing status

Jim Kilmer

RICH support stand bid package

Mark Messier

RICH electronics

Gary Smith

NCAL Stand drawings

Leon Beverly

Chamber discriminator adapter board.

Tim Bergfeld

TOF

Virgil Bocean

Alignment

AOB


Progress Updates and Issues

Leon Beverly's meeting summaries in italics.

Upstream Beamline

BEAM - Beamline

Chuck Brown:

The opening of MC6 target pile has begun. It takes a few weeks to get all concrete blocks off of the top.

UBL - Upstream Beamline Detectors

Kilmer:

Has 10" beam pipe, but needs the 12" beampipe.

Targets

TGTW - Target Wheel

CTGT - Cryogenic Targets

NTGT - NuMI (MINOS) Target

TPC - Time Projection Chamber

Ron Soltz:

  • Gating Grid talks (emails) continue, schematics may turn up (see following)
  • Visited LBNL and picked up following
    • More schematics from Fred Bieser
    • Order boxes from archives, full story at 3PM
    • Spare pre-amps and SCA's
    • Work on booting embedded linux kernel (David A. and Mike) continues

    See TPC on Web for more info on DAQ

Magnets

Peter Barnes

Grout order has been placed. Five kits in stock to be delivered this week; balance in 2 weeks.

Installation procedure in signature chain. Current plan is to start assembly May 14th. However, prior to starting, the 3 Rosie bases pieces of steel must have a 1 ¼" plate welded to the bottom of each. A temporary barrier wall will be installed in US MC7 Tuesday, May 7th.

JGG - Jolly Green Giant

Rosy

CKOV - Cerenkov

David Lange:

Ingrid Fang:

The design work has completed including the track plates. Gary can start working on this after he finishes the support stand. A general assembly drawing is also required to include Chamber 1, CKOV unit,, Chamber2 support stand, cart and track plates.

Length of track plate to be as long as possible i.e. butt up to JGG base US and Rosie base DS. Completion of all drawings pushed back from next week to an additional 2 weeks.

DC - Drift Chambers

Adam Bujak:

The remaining things to do are:

  1. Making ~100 cables for discriminator-to-tdc connection (have them already at Lab.6). Gyula Zilizi has promissed to help.
  2. Adjusting power voltages in the discriminator crates (do not know yet how).
  3. Some programming (trivial).
  4. Find (at least) 2 additional scintillators for the trigger and set them up.
  5. Get 3-phase power at Lab.6 (Leon promissed to organize it).
  6. WAIT for the gas and the adapters.

I belive, that I will be able to take care of data taking with the first chamber. The most useful help would be in the data analysis (defining chamber geometry, track recognition, etc.) and preparation of the remaining chambers for testing (capacitance measurement - proven useful, attaching preamp.supports and shielding).

I have found some number of bad preamps and preamp-to-disriminator cables. Some discriminator boards were so dirty I had to wash them. After the procedure, two discriminator boards (out of 60) do not work. I do not know, what has killed them (I didn't risk to try them before taking out of ~1 mm leyer of dirt). All the discriminators I'm using are meant for the small crates, they are NOT exchangeable with those in the large crates stored in PC4. What follows from all of that, is that we need to test the stuff (cables for sure) before the final installation - independently from our test.

At the moment I'm looking at signals from ampplifiers by sending a (square) pulse from a pulser to the cathodes. The front of the pulse is much too fast, so the amplifier response is quite "dirty". But it's good enouch for setting up timing and checking if the preamps are alive. There is an indication of quite large differences in amplification of different channels. If this is true, we need to think about providing threshold voltages to individual discriminator boards (in "my" crates, same voltage is applied to the entire crate; I do not know, how the backplanes of the PC4 crates are wired).

Ingrid Fang:

The inner frame and outer frame drawings have been checked. Gary needs to make a assembly drawing to show how the inner frame works with the outer frame.

LLNL placed PO for discriminator pc adapter board; two additional 208V circuits needed by Adam to power up discriminator crates at lab 6 will be installed Tuesday, May 7th; DC#2 inner & outer frame drawings checked, assembly drawing next.

TOF - Time of Flight

Andrew Godley:

I don't know how much of this has already been reported, but Tim is away at the moment. This is what Carl and I have to report:

  • We have samples of the full sized scintillator bars on order.
  • We have 3 2" photo tubes that we are currently test.
  • We have made a sample light pipe out of plastic, and now have the UVT [Ultra violet transmitting... the type of acrylic we will use to make the light tubes. ] to make a working sample. The first was to test the machining process.

Need physical design parameters & its location

RICH - Ring Imaging Cerenkov

Peter Barnes

RICH casters have been ordered from Castor Corporation, delivery in 1 week. RICH Stand and track plate order is with Betty.

Contract with Burns Machine to build support stand under way, but no PO yet.

NCAL - Calorimeter

Ingrid Fang:

I have not had time to check the drawings yet. But I will do it next.

DAQ - Data Acquisition

MC - Monte Carlo

Installation

Alignment

Virgil will have the floor marked for base steel location on Tuesday.

MC7 Enclosure and Counting House

Peter Barnes

MC7 Enclosure materials have been ordered from Arch Technology.

Meetings

Project Management

Next Systems Call

The next call will be Thursday, 9 May 2002, at 3:00 CDT.


PDB, 5/2/02