E907 Installation Conference Call Minutes

9 May 2002

Phone Number

Access Code:

775-785-1944

536495

Contents

Agenda

Progress Updates and Issues

  1. Upstream Beamline
    1. BEAM - Beamline
    2. UBL - Upstream Beamline Detectors
  2. Targets
    1. TGTW - Target Wheel
    2. CTGT - Cryo Targets
    3. NTGT - NuMI (MINOS) Target
  3. TPC - Time Projection Chamber
  4. Magnets
    1. JGG - Jolly Green Giant
    2. Rosy
  5. CKOV - Cerenkov
  6. DC - Chambers
  7. TOF - Time of Flight
  8. RICH - Ring Imaging Cerenkov
  9. NCAL - Calorimeter
  10. DAQ - Data Acquisition
  11. MC - Monte Carlo
  12. Installation
    1. Alignment
  13. MC7 - Enclosure and Counting House
  14. Meetings
  15. Project Management

Next Call


Agenda

Time (CST)

Dur (min)

Lead

Topic

3:00

5'

call setup

Chuck Brown

BEAMS

Mike Heffner

Beam CKOV

Ron Soltz

TPC

Jim Ellermeier
Leon Beverly

Magnets
MC7 Preparation

Ingrid Fang
Gary Johnson

CKOV Stand design and drawing status

Peter Barnes
Mark Messier

RICH support stand
RICH electronics

Leon Beverly

Chamber testing.

Tim Bergfeld

TOF

Virgil Bocean

Alignment

AOB


Progress Updates and Issues

Leon Beverly's meeting summaries in italics.

Upstream Beamline

BEAM - Beamline

Chuck Brown:

Opening of target pile is progressing, about 25% to 30% of blocks off the top; beam design is progressing, but need transport deck from Hartouni.

UBL - Upstream Beamline Detectors

No update; one day need detailed drawing of pipe with cerenkov heads & other beamline detectors.

Targets

TGTW - Target Wheel

CTGT - Cryogenic Targets

NTGT - NuMI (MINOS) Target

TPC - Time Projection Chamber

Ron Soltz:

Main LBNL archives to be transferred to LLNL.

Ingrid Fang:

I have collected the information from the E907 web site. I also looked the unit in the MC7. I will ask specific questions in the meeting.

Support needs to center TPC in JGG with minor adjustments for alignment done with existing 3 point under carriage; Ron Soltz reports ongoing DAQ, see Web page for documentation.

Magnets

Installation/JHA procedure to John Cooper for review & signature; temporary barrier between US MC7 & DS MC7 is complete; preparing to start removing DS roof in sections.

JGG - Jolly Green Giant

Rosy

CKOV - Cerenkov

Ingrid Fang:

Ready to be drawn by Gary. No change since last week.

Support cart ready for Gary to draw, completion expected in 2 weeks.

DC - Drift Chambers

Ingrid Fang:

Gary is working on my mark-ups.

PO for discriminator adapter boards placed, no deliver date yet; DC#2 &endash; Gary is working on drawing mark-ups; Kilmer to assign engineer to start design on supports for chamber #5 & #6.

TOF - Time of Flight

RICH - Ring Imaging Cerenkov

Mark Messier:

Here's my summary of the RICH electronics status:

As I'm sure you know, we've decided it would be too big a job to try to unsolder all the Russian FEU-60 bases so we'll be making use of the existing high voltage distribution system. Sten is working on the P.O. for the parts that are not involved with HV generation while he works on the redesign for the change in the HV plan. This is to keep work on the BTeV and CKM designs going. The next step for the MIPP version of the electronics is to inspect the RICH PMT box to see how to make the physical connections between the anode signals and the readout cards. I'm hoping Andrei and I can help with that later next week before the meeting.

Andrei and I have been looking into options for replacing the Russian HV supplies. Earl says they worked fine during the initial PMT testing and so may be reusable but some issues are: lack of FNAL support, questionable spares and spare parts, and lack of remote computer control and monitoring. There may also be safety issues, although SELEX managed to get operation of these supplies approved. For 32 tubes typical numbers are 2kV @ 7mA for 32 FEU-60's, and ~2kV @ 16 mA for 32 HAMA-R760's which is a lot more power per channel than the typical high density HV supply can put out. Andrei and I checked FNAL PREP and there's nothing there can reasonably meet these spec's. There may be a CAEN system which would do the job (a single mainframe w/ 10 cards of 9 channels each), although even that system is on the edge -- I need better numbers about the PMT base resistances and preferred HV before I can tell for sure.

PO for rails (delivery first week of June) and support stands (delivery end of June) placed with Burns Machinery; electronics &endash; HV distribution to PMT will remain unchanged, but new readout board will be built.

NCAL - Calorimeter

Ingrid Fang:

I almost finished the checking process. Gary needs to make a assembly drawing to show how the existing stand slides on top of the new one.

DAQ - Data Acquisition

David Asner:

Successfully built and booted a linux kernel (help from Dave Slimmer) and commenced testing.

MC - Monte Carlo

Installation

Alignment

MC7 Enclosure and Counting House

Meetings

Project Management

Next Systems Call

The next call will be Thursday, 16 May 2002, at 3:00 CDT.


PDB, 5/28/02