E907 Installation Conference Call Minutes
|
16 May 2002 |
Location |
Phone Number |
Access Code |
|
WH-11SW |
775-785-1944 |
536495 |
Agenda
|
Time (CST) |
Dur (min) |
Lead |
Topic |
|---|---|---|---|
|
3:00 |
5' |
call setup |
|
|
Chuck Brown |
BEAMS |
||
|
Mike Heffner |
Beam CKOV |
||
|
Ron Soltz |
TPC |
||
|
Leon Beverly |
Magnets Install Schedule |
||
|
Ingrid Fang |
CKOV Stand design and drawing status |
||
|
Leon Beverly |
RICH rail installation schedule |
||
|
Leon Beverly |
Chamber brackets, adapter cards. |
||
|
Tim Bergfeld |
TOF |
||
|
Virgil Bocean |
Alignment |
||
|
AOB |
Leon Beverly's meeting summaries in italics.
BEAM - Beamline
Chuck Brown:
Minimum progress on pile opening, riggers moved to a higher priority job.
UBL - Upstream Beamline Detectors
Beam CKOV:
Jim will use beam pipe recently removed from MW6 for beam pipe in MC7. The pipe is slightly radioactive, low class 1 - 0.1mr/hr
TGTW - Target Wheel
CTGT - Cryogenic Targets
NTGT - NuMI (MINOS) Target
Ingrid is gathering design parameter on the support cart.
John [Cooper] has reviewed the installation procedure. I expect to have all signatures on Monday. So steel setting will commence on Tuesday, the 21st.JGG - Jolly Green Giant
Rosy
Drawings for the inner & outer stands are complete, beginning the drawing for support stand, then need an assembly drawing.
Awaiting discriminator adapter boards so an entire chamber can be readout at once.Ed LaVallie is commencing design on support stands for the Iowa chambers, chambers #5 & #6
Anticipating deliver of rails and stand in June.
Alignment
The next call will be Thursday, May 23, 2002, at 3:00 CDT in WH-11SW.