E907 Installation Conference Call Minutes

11 July 2002

Location

Phone Number

Access Code

WH-11SW

775-785-1944

536495

Contents

Agenda

Progress Updates and Issues

  1. Upstream Beamline
    1. BEAM - Beamline
    2. UBL - Upstream Beamline Detectors
  2. Targets
    1. TGTW - Target Wheel
    2. CTGT - Cryo Targets
    3. NTGT - NuMI (MINOS) Target
  3. TPC - Time Projection Chamber
  4. Magnets
    1. JGG - Jolly Green Giant
    2. Rosy
  5. CKOV - Cerenkov
  6. DC - Chambers
  7. Gas Systems
  8. TOF - Time of Flight
  9. RICH - Ring Imaging Cerenkov
  10. NCAL - Calorimeter
  11. DAQ - Data Acquisition
  12. MC - Monte Carlo
  13. Installation
    1. Alignment
  14. MC7 - Enclosure and Counting House
  15. Meetings
  16. Project Management

Next Call


Agenda

Time (CST)

Dur (min)

Lead

Topic

3:00

5'

call setup

Chuck Brown

BEAMS

Jim Kilmer

Beam CKOV

Ingrid Fang

TPC

Jim Ellermeier

Rosie Welding Spec

Ingrid Fang

CKOV/DC2 stand quotes

Mark Messier

RICH

Rajendran Raja
Dave Northacker

Chamber testing
Amplifier brackets

Tim Bergfeld

TOF

Virgil Bocean

Alignment

Leon Beverly

MC7 Roof Installation

AOB


Progress Updates and Issues

Leon Beverly's meeting summaries in italics.

Upstream Beamline

BEAM - Beamline

Chuck Brown's next Beams meeting is scheduled for July 15th; Currently, Ed Hartouni is progressing on beam design by modeling beam at different energies.

UBL - Upstream Beamline Detectors

Beam CKOV

Jim Kilmer is compiling a parts list to gain remote control on 2nd CKOV. A drawing is in the preliminary stages. Note: 0.36 mil mirror movement = 27 degrees angle movement; available stepper motors can do 200 steps/revolution. Dan Schoo is an initial contact for information regarding hardware to compute interface. Readouts such as gas pressure, mirror position need to go to E907 computer.

Mike Heffner &endash; Raja encourages going ahead and get mirrors resurfaced if cost is $600 or less.

Three "small" E690 chambers will be used in secondary beam line, one before the first CKOV, one between the CKOVs and one after the CKOVs.

Targets

TGTW - Target Wheel

CTGT - Cryogenic Targets

NTGT - NuMI (MINOS) Target

TPC - Time Projection Chamber

Ingrid Fang

TPC/ Hydrogen Target Stationary Stand Update: This stationary stand design has been completed. The allowable load on the rail is limited to 1000 pounds which is greater than the target weight estimated by Kilmer. The stand is kept to 10.5 feet long as I originally planed.

TPC Support Frame Update: ----- I will work on it next.

Peter Barnes

Setting up stick test stand in MC7 to support repair of dead channels.

Magnets

JGG - Jolly Green Giant

JGG LCW headers under fabrication.

Rosy

Welding specs for Rosie's steel are complete, steel material is on order. Welding will be done over the week of July 15th.

Painting is next.

CKOV - Cerenkov

Ingrid Fang

CKOV/Chamber #2 Quote Update: ------ Two more quotes will due on 7/15/02.

DC - Drift Chambers

Lab 6 test stand

50% of electronics is now working. Transfer frame &endash; Build at Columbia? No drawings, but they know how to assemble. Small parts are on order.

Iowa chambers

Support stand design in progress

 

Gas Systems

Terry Tope:

I talked to the Fermilab ES&H about C4F10. Basically they would prefer a gas with global warming potential is not vented to the atmosphere on purpose. They asked if it was practical for 3M to take the gas back or to have a system to reuse it. If E907 said neither approach was practical for one reason or another, they would have no problem with the experiment venting the C4F10. So if its easy to prevent venting, thats what they would want done. To vent it it, we would have to show that 3M does not want it back and its not practical to reuse it. I contacted 3M and their product name for C4F10 is PFG-5040. They recycle the liquid fluorocarbons but I'm waiting to hear back about gas fluorocarbons. Attached is a .pdf with the 3 cylinder sizes and the cost per standard cubic foot. Its very expensive. I don't know how much you plan on using for the experiment duration, but filling 100 ft^3 CKOVs will be expensive. So re-use might be the cost effective thing to do. I think KTeV had a Xenon recycling system. I will try and find out how much that cost for a rough estimate on such a system.

TOF - Time of Flight

Carl Rosenfeld

We continue to work on the design and prototyping of the TOF system. So far we have achieved a resolution "on the bench" better than 200ps. Ongoing activities include:

  1. Construction of an 0.02T Helmholtz coil -- the machining is finally underway -- for exercising PMTs with shield in a magnetic field;
  2. Preparation of a large-area cosmic ray telescope for rapid and comprehensive resolution studies;
  3. Design of the interface from the scintillator to the PMT, both optical aspects and mechanical aspects;
  4. Simulations of the light collection process both to facilitate item C) and to understand the relationship between discriminator threshold and resolution;
  5. Various measurements to constrain the simulations of item D);
  6. Reevaluation of multi-hit inefficiency for our most recent system designs;
  7. Waiting for the money.

The most important TOF problem that is not getting adequate attention at this time is a simulation aimed at understanding the damage that the TOF wall does to event reconstruction and to momentum resolution.

The effect of Rosie's fringe field on PMTs is understood, the closest PMT will be 30cm off US mirror plate of Rosie.

RICH - Ring Imaging Cerenkov

RICH sitting on new supports and rails.

Mark Messier

  • Tested existing supplies, 7 of 8 power up. I understand interlock system. Still trying to track down prefered voltages etc.
  • PO for 5 read out boards has gone out.
  • Sten is revising cost and schedule for Harvard/LLNL MOU.
  • Andre has the powerPC working. Started on DAQ raw file/event format.

Andre Lebedev

I have only one thing to say is that we are successfully communicating through VME back plane with the PPC. Everything is working beautifully as of beginning of this week.

NCAL - Calorimeter

DAQ - Data Acquisition

MC - Monte Carlo

Installation

Alignment

JGG (mean steel [the center of the aperture]) = 8985.207 inches, and - FYI: Rosie (mean steel) = 8985.026 inches; Therefore, the beam height in MC7 determined as the centerline of the installed JGG (as per Raja suggestion) is 8985.207 inches. As a result, the beam height with respect to the floor is 81.275 inches.

MC7 Enclosure and Counting House

Material deliver expected July 19th. The roof installation to commence on July 22nd.

Meetings

Project Management

Next Systems Call

The next call will be Thursday, <date> 2002, at 3:00 CDT in WH-11SW.


PDB, 7/18/02