E907 Installation Conference Call Minutes
|
25 July 2002 |
Location |
Phone Number |
Access Code |
|
WH-11SW |
805-240-9463 |
536495 |
Agenda
|
Time (CST) |
Dur (min) |
Lead |
Topic |
|---|---|---|---|
|
3:00 |
5' |
call setup |
|
|
Chuck Brown |
BEAMS |
||
|
Mike Heffner |
Beam CKOV |
||
|
Peter Barnes |
TPC |
||
|
Jim Ellermeier |
Magnets |
||
|
Ingrid Fang |
CKOV Stand fabrication |
||
|
Mark Messier |
RICH electronics |
||
|
Adam Bujak |
Chamber testing. |
||
|
Ed La Vallie |
Iowa chamber stands. |
||
|
Virgil Bocean |
Alignment |
||
|
Leon Beverly |
MC7 building installation |
||
Leon Beverly's meeting summaries in italics.
BEAM - Beamline
Chuck Brown has a composite drawing of the primary & secondary beam line produced &endash; Chuck: forward to Peter of inclusion on MIPP Web page.
Starting Tuesday, 7/30 &endash; survey marks will be installed of primary beam elements in MC5 & MC6.
UBL - Upstream Beamline Detectors
BCKOV
Raja request we proceed with resurfacing mirrors.
In addition to support stands for the CKOVs, support stand will be needed for 3 &endash; E690 beam chambers.
TGTW - Target Wheel
CTGT - Cryogenic Targets
NTGT - NuMI (MINOS) Target
Peter reports DAQ is operational at MC7; Bob Jones is executing a "fix" on 2 electronics boards. If the fix works, all boards will be repaired. Mike Heffner & David Asner will arrive Monday, 7/29 to continue testing boards.Stationary support stand drawing complete, Ingrid to check; platform frame design estimated completion in 3 weeks; at some point mounting holes will need to be drilled in JGG steel.
JGG - Jolly Green Giant
JGG LCW headers under fabrication
Rosy
Welding specs for Rosie's steel are complete, steel material is here. Welding will be done over the week of August 5th; painting is next.
POs placed by Livermore for fabrication of cart, rails and DC#2 inner/outer frame. Delivery is due 3 weeks.
Lab 6 test stand - 100% of preamp electronics is now workingTransfer frame &endash; Build at Columbia?
Raja urges Dave to speed up fabrication of chamber bracket work.
Iowa chambers &endash; support stand design in progress; Gary will do drawings in between work on two TPC stands.
VME cards have been delivered; PO generated for the 32 channel boards.
Alignment
Virgil will send out new beam sheet & updated file on MC7 survey. Also, during the next pass in MC7, he will have rails under the RICH documented &endash; one wheel of the RICH is up in the air.
Roof installation in progress &endash; completion about 8/2; PK A/C needs attention &endash; LB to push; Andrey Bobyshev is the CD contact for network upgrade. He is working on a proposal to get necessary hardware in place at MC7 & PKs.
The next call will be Thursday, 1 August 2002, at 3:00 CDT in WH-11SW.