E907 Installation Conference Call Minutes

1 August 2002

Location

Phone Number

Access Code

WH-11SW

805-240-9463

536495

Contents

Agenda

Progress Updates and Issues

  1. Upstream Beamline
    1. BEAM - Beamline
    2. UBL - Upstream Beamline Detectors
  2. Targets
    1. TGTW - Target Wheel
    2. CTGT - Cryo Targets
    3. NTGT - NuMI (MINOS) Target
  3. TPC - Time Projection Chamber
  4. Magnets
    1. JGG - Jolly Green Giant
    2. Rosy
  5. CKOV - Cerenkov
  6. DC - Chambers
  7. TOF - Time of Flight
  8. RICH - Ring Imaging Cerenkov
  9. NCAL - Calorimeter
  10. DAQ - Data Acquisition
  11. MC - Monte Carlo
  12. Installation
    1. Alignment
  13. MC7 - Enclosure and Counting House
  14. Meetings
  15. Project Management

Next Call


Agenda

Time (CST)

Dur (min)

Lead

Topic

3:00

5'

call setup

Chuck Brown

BEAMS

Mike Heffner

Beam CKOV

Mike Heffner
Ingrid Fang

TPC

Leon Beverly

Magnets

Peter Barnes

CKOV and DC2 stands fabrication

Mark Messier

RICH electronics

Adam Bujak

Chamber testing.

AOB


Progress Updates and Issues

Leon Beverly's meeting summaries in italics.

Upstream Beamline

BEAM - Beamline

UBL - Upstream Beamline Detectors

BCKOV

US CKOV beam pipe may have to be shortened to accommodate E690 wire chambers that will be located US, between and DS of the CKOVs. Gary Smith will talk to Beams side drafter and get exact dimension and space available on a drawing.

Mike Heffner will discuss mirror re-coating with Jim K and commence paper work to get it done.

Targets

TGTW - Target Wheel

CTGT - Cryogenic Targets

NTGT - NuMI (MINOS) Target

TPC - Time Projection Chamber

Stick repair: replacing the "lead" chip does not repair a single group of channels because it was found that individual channels have bad components &endash; repairs & testing continue.

Platform frame design estimated completion in 2 weeks, 70% complete; at some point mounting holes will need to be drilled in JGG steel.

Magnets

Power supplies will be located in ME6 area of the Detector building, thus the DC will be transported down to the magnets from that location.

JGG - Jolly Green Giant

Rosie

Rosie steel welding not yet scheduled &endash; maybe next week.

CKOV - Cerenkov

Cart, rails and DC#2 inner/outer frame. Delivery is due mid August.

DC - Drift Chambers

Testing continues.

Dave will have the bracket & tray of one chamber completed next week.

Iowa chambers &endash; support stand design in progress

TOF - Time of Flight

RICH - Ring Imaging Cerenkov

5 - VME boards being stuffed at Fermilab; layout of 32 channel boards nearly complete. The boards will also be stuffed at Fermilab, and then preliminary testing will be done before sending the boards to Harvard for production testing.

NCAL - Calorimeter

DAQ - Data Acquisition

MC - Monte Carlo

Installation

Alignment

MC7 Enclosure and Counting House

Roof installation in progress &endash; completion about 8/7 - then insulation of roof.

Meetings

Project Management

Next Systems Call

The next call will be Thursday, 8 August 2002, at 3:00 CDT in WH-11SW.


PDB, 8/21/02