E907 Installation Conference Call Minutes
|
1 August 2002 |
Location |
Phone Number |
Access Code |
|
WH-11SW |
805-240-9463 |
536495 |
Agenda
|
Time (CST) |
Dur (min) |
Lead |
Topic |
|---|---|---|---|
|
3:00 |
5' |
call setup |
|
|
Chuck Brown |
BEAMS |
||
|
Mike Heffner |
Beam CKOV |
||
|
Mike Heffner |
TPC |
||
|
Leon Beverly |
Magnets |
||
|
Peter Barnes |
CKOV and DC2 stands fabrication |
||
|
Mark Messier |
RICH electronics |
||
|
Adam Bujak |
Chamber testing. |
||
|
AOB |
Leon Beverly's meeting summaries in italics.
BEAM - Beamline
UBL - Upstream Beamline Detectors
BCKOV
US CKOV beam pipe may have to be shortened to accommodate E690 wire chambers that will be located US, between and DS of the CKOVs. Gary Smith will talk to Beams side drafter and get exact dimension and space available on a drawing.
Mike Heffner will discuss mirror re-coating with Jim K and commence paper work to get it done.
TGTW - Target Wheel
CTGT - Cryogenic Targets
NTGT - NuMI (MINOS) Target
Stick repair: replacing the "lead" chip does not repair a single group of channels because it was found that individual channels have bad components &endash; repairs & testing continue.Platform frame design estimated completion in 2 weeks, 70% complete; at some point mounting holes will need to be drilled in JGG steel.
Power supplies will be located in ME6 area of the Detector building, thus the DC will be transported down to the magnets from that location.JGG - Jolly Green Giant
Rosie
Rosie steel welding not yet scheduled &endash; maybe next week.
Cart, rails and DC#2 inner/outer frame. Delivery is due mid August.
Testing continues.Dave will have the bracket & tray of one chamber completed next week.
Iowa chambers &endash; support stand design in progress
5 - VME boards being stuffed at Fermilab; layout of 32 channel boards nearly complete. The boards will also be stuffed at Fermilab, and then preliminary testing will be done before sending the boards to Harvard for production testing.
Alignment
Roof installation in progress &endash; completion about 8/7 - then insulation of roof.
The next call will be Thursday, 8 August 2002, at 3:00 CDT in WH-11SW.