E907 Installation Conference Call Minutes
|
8 August 2002 |
Location |
Phone Number |
Access Code |
|
WH-11SW |
805-240-9463 |
536495 |
Agenda
|
Time (CST) |
Dur (min) |
Lead |
Topic |
|---|---|---|---|
|
3:00 |
5' |
call setup |
|
|
Chuck Brown |
BEAMS |
||
|
Mike Heffner |
Beam CKOV |
||
|
Peter Barnes |
TPC |
||
|
Leon Beverly |
Magnets |
||
|
Mark Messier |
RICH electronics |
||
|
Adam Bujak |
Chamber testing. |
||
|
Tim Bergfeld |
TOF |
||
|
Virgil Bocean |
Alignment |
||
|
AOB |
Leon Beverly's meeting summaries in italics.
BEAM - Beamline
UBL - Upstream Beamline Detectors
BCKOV
The position of last quad in beam line will cause the US vacuum pipe to be shortened about 3 feet.
TGTW - Target Wheel
CTGT - Cryogenic Targets
NTGT - NuMI (MINOS) Target
Testing continues on stick repairs; support stand design 75%.
JGG - Jolly Green Giant
Rosie
Rosie steel welding complete; magnet painting next
E690 Chambers
Work continues on brackets & trays.
Iowa Chambers
Support stand design in progress.
Alignment
Virgil will email spreadsheets that show data on recent surveys of MC7 + RICH rail elevations. Completion of survey through target pile cannot be completed until last B2 magnet is removed.
Roof installation in progress &endash; completion about 8/19 - insulation of roof week of 8/19; OH doors are being installed.
The next call will be Thursday, 22 August 2002, at 3:00 CDT in WH-11SW.