E907 Installation Conference Call Minutes

29 August 2002

Location

Phone Number

Access Code

WH-11SW

805-240-9463

536495

Contents

Agenda

Progress Updates and Issues

  1. Upstream Beamline
    1. BEAM - Beamline
    2. UBL - Upstream Beamline Detectors
  2. Targets
    1. TGTW - Target Wheel
    2. CTGT - Cryo Targets
    3. NTGT - NuMI (MINOS) Target
  3. TPC - Time Projection Chamber
  4. Magnets
    1. JGG - Jolly Green Giant
    2. Rosy
  5. CKOV - Cerenkov
  6. DC - Chambers
  7. TOF - Time of Flight
  8. RICH - Ring Imaging Cerenkov
  9. NCAL - Calorimeter
  10. DAQ - Data Acquisition
  11. MC - Monte Carlo
  12. Installation
    1. Alignment
  13. MC7 - Enclosure and Counting House
  14. Meetings
  15. Project Management

Next Call


Agenda

Time (CST)

Dur (min)

Lead

Topic

3:00

5'

call setup

Chuck Brown

BEAMS

Mike Heffner

Beam CKOV

Ron Soltz

TPC

Leon Beverly

Magnets

Leon Beverly

CKOV stand

Mark Messier

RICH

Adam Bujak

Chamber testing

Ed LaVallie
Ingrid Fang

Iowa chamber stands
DC 3 & 4 stands

Tim Bergfeld

TOF

Virgil Bocean

Alignment

AOB


Progress Updates and Issues

Leon Beverly's meeting summaries in italics.

Upstream Beamline

BEAM - Beamline

Chuck Brown:

Lead contamination is delaying final removal of equipment from the target pile, however, clean up is in progress; manpower is an issue because of "higher" priority jobs in BEAMS

UBL - Upstream Beamline Detectors

BCKOV

Gary is updating drawing at interface with BEAMS

Targets

TGTW - Target Wheel

CTGT - Cryogenic Targets

NTGT - NuMI (MINOS) Target

TPC - Time Projection Chamber

Stationary stand drawings ready for a quote; movable stand drawings are in progress.

Magnets

Painting in progress; spaces between coils on the US & DS ends of Rosie need to be shimmed

JGG - Jolly Green Giant

Rosie

CKOV - Cerenkov

Installing cart rails starting 8/29.

DC - Drift Chambers

E690 Chambers

DC#2 inner/outer frame delivered 8-28-02

Transfer frame weldment going to Fermilab for final assembly; final design of air and cable way close to done; Dave will also determine CFM of air flow and the style of fans needed so fans can be procured.

Iowa Chambers

Support stand design in progress, drawings started; RMH racks need chilled water, 18 °C input, 2 gpm/rack, heat load is 2500W/rack, two racks; Also discussed options for repairing chambers in place. A small lift will be needed to support chamber planes during separation.

TOF - Time of Flight

Tim Bergfeld:

We have materials for a prototype bar in the simple design. This design has a 5x5x300cm bar of scintillator with two 2 inch phototubes attached to the ends. The prototype bar has been tested with cosmics and provides slightly better than 150ps resolution in the center of the bar and a bit less than 100ps close to one of the phototubes. We have fabricated Winston cones from UV Transparent acrylic.

There is some concern that a 5cm thick piece of scintillator is too much material in the beam line and Raja has been looking at the Monte Carlo to study if there is a problem. The one result we have heard from Raja is that there is a substantial production of e+e- pairs from photons in the center part of the detector. These photons appear to be in the beam spot of the detector. At this point we plan to open a hole in that region to solve this problem.

A second design with thinner scintillator in the central aperture region of ROSY has been done and we have ordered phototubes and scintillator to test that design. Work is ongoing on the optical transitions from the scintillator to the phototubes for this design.

A Helmholtz coil has been fabricated to test the magnetic shielding for the phototubes. From Bob Wand's calculations, the simple design will put the phototubes in an area with a moderate magnetic field of about 3-9 Gauss. The shielding of our tubes will be tested with our coil so that we know what resolution to expect. The more complicated design puts phototubes in a significantly higher field of 20-60 Gauss. Thus shielding work is going to be of some importance if we must use the more complicated design.

Additionally work is being done to look more closely at the single photo-electron response of these tubes so that we can properly calibrate the signal that we observe.

Finally a larger cosmic telescope is being constructed with RPC reclaimed by South Carolina from FOCUS so that we can more quickly make measurements of the production counters.

The last issue is simply that we are awaiting word on funding to purchase the materials needed for the TOF Counter. We expect to hear from SSAAP hopefully soon.

Overall size will be about H-3m X W-5m X 10cm deep (material + unistrut frame). Material in beam is expected to be about 5cm thick. The frame will mount about 5cm off of the US Rosie mirror plate.

RICH - Ring Imaging Cerenkov

NCAL - Calorimeter

DAQ - Data Acquisition

MC - Monte Carlo

Installation

Alignment

Still awaiting removal of B2 from target pile so final survey thru MC5, 6 & 7 can be documented.

MC7 Enclosure and Counting House

DS roof installation complete, insulation installation started 8/28.

Meetings

Project Management

Next Systems Call

The next call will be Thursday, 5 September 2002, at 3:00 CDT in WH-11SW.


PDB, 9/12/02