E907 Installation Conference Call Minutes

14 November 2002

Location

Phone Number

Access Code

WH-3 NE

805-240-9463

536495

Contents

Progress Updates and Issues

  1. Upstream Beamline
    1. BEAM - Beamline
    2. UBL - Upstream Beamline Detectors
  2. Targets
    1. TGTW - Target Wheel
    2. CTGT - Cryo Targets
    3. NTGT - NuMI (MINOS) Target
  3. TPC - Time Projection Chamber
  4. Magnets
    1. ZipTrack
    2. JGG - Jolly Green Giant
    3. Rosy
  5. CKOV - Cerenkov
  6. DC - Chambers
    1. DC1-4 (E690 Chambers)
    2. DC5 & DC6 (Iowa Chambers)
  7. TOF - Time of Flight
  8. RICH - Ring Imaging Cerenkov
  9. ECAL - EM Calorimeter
  10. NCAL - Hadron Calorimeter
  11. Gas Systems
  12. DAQ - Data Acquisition
  13. MC - Monte Carlo
  14. Installation
    1. Alignment
  15. MC7 - Enclosure and Counting House
  16. Meetings
  17. Project Management

Next Call


Progress Updates and Issues

Leon Beverly's meeting summaries in italics.

Upstream Beamline

BEAM - Beamline

Waiting for FY03 funding to resume work in MC5/MC6.

UBL - Upstream Beamline Detectors

BCKOV

Jim K has package ready and will soon send out first mirror to get modified & resurfaced; Probably need new PMTs (2” tubes); with planned vacuum pumps, a complete gas change will take 45 minutes to 1 hour. The vacuum will be about 10 microns after 45 minutes.

Targets

TGTW - Target Wheel

CTGT - Cryogenic Targets

NTGT - NuMI (MINOS) Target

TPC - Time Projection Chamber

Bob Jones group has fixed shorts of some sticks. Ten sticks have shorts, and a few others have chip problems; Livermore is placing the PO to procure TPC support stands.

Magnets

Main LCW header installation along MC7 and over to magnets will commence about 11/20.

ZipTrack

Brackets to hold hall probes are designed and are being fabricated.

Relocated ziptrack from lab 8 to MC7 about 11/26.

JGG - Jolly Green Giant

DC leads have been connected. Electrically the coils are ready to be energized.

Rosie

DS side of Rosie coil shims installation will be done 11/18. That work will be followed by connect LCW hoses. Fabrication of Bus jumpers to series coils is in process. Klixons need to be connected.

CKOV - Cerenkov

DC - Drift Chambers

DC1-4 (E690 Chambers)

DC3 - Looking at how to tie chamber stand to floor.

DC5 & DC6 (Iowa Chambers)

Also looking at tie down attachment

TOF - Time of Flight

RICH - Ring Imaging Cerenkov

Equipment (chillers, pumps, etc.) locations need to be determined.

ECAL - EM Calorimeter

HA in progress, also need lift to handle 400 lb panels and lift them to about 10 feet.

NCAL - Calorimeter

Gas Systems

DAQ - Data Acquisition

MC - Monte Carlo

Installation

Alignment

Laser tracker survey of MC7 complete. Virgil to reduce computations to spreadsheet.

MC7 Enclosure and Counting House

Meetings

Project Management

Next Systems Call

The next call will be Tuesday, 26 November 2002, at 1:00 CDT in WH-2NE, Snake Pit.


PDB, 12/10/02