E907 Installation Conference Call Minutes
|
03 December 2002 |
Location |
Phone Number |
Access Code |
|
WH-2 NE |
865-673-6703 |
334823 |
- Upstream Beamline
- Targets
- TPC - Time Projection Chamber
- Magnets
- CKOV - Cerenkov
- DC - Chambers
- TOF - Time of Flight
- RICH - Ring Imaging Cerenkov
- ECAL - EM Calorimeter
- NCAL - Hadron Calorimeter
- Gas Systems
- DAQ - Data Acquisition
- MC - Monte Carlo
- Installation
- MC7 - Enclosure and Counting House
- Meetings
- Project Management
Leon Beverly's meeting summaries in italics.
BEAM - Beamline
Raja reports that Tom Kobilarcik will assign coordinates to MC5 & MC6 area beam line elements.
UBL - Upstream Beamline Detectors
BCKOV
Win still pursuing motorizing manually controlled mirrors in one CKOV.
TGTW - Target Wheel
CTGT - Cryogenic Targets
NTGT - NuMI (MINOS) Target
POs for stationary stand & cart/rails have been placed. Delivery about 4 weeks. Bob J. has his supply of sticks repaired. Peter to deliver more stick to him 12/14.
Main LCW header installation along MC7 and over to magnets completed expected 12/6. 2nd pORC walk through 12/9.
ZipTrack
Relocate ziptrack from lab 8 to MC7 Tuesday, 12/10.JGG - Jolly Green Giant
Rosie
LCW hoses will be installed the week of 12/9. Bus jumpers to series coils finished about 12/11. Klixons & hall probes need to be connected.
DC1-4 (E690 Chambers)
Electronics test stand is operational. After testing at lab 6, the stand will be moved to IIT.
Support stand drawings down to the details. Assembly drawing will take a week.
DC5 & DC6 (Iowa Chambers)
Support stand drawings going out for a fabrication quote on 12/5 (10 day quote period).
Nick did some more checking on the KTeV recycler. KTeV has a note 156 that does a reasonable job of describing the recycler system as designed. Can the recycler be used on the Iowa chamber gas? more evaluation, on both the recycler and which gases will be used, is needed.
Looked at HyperCP counters, but they had only about 1/2 the number needed, and [left out of previous minutes] phototubes would also have to be purchased.
Carl estimates TOF cost at $248K; also discussion of RPC/Harp, etc.
Will have 8 channels/unit, 640 total channels. Assembly will begin after all workers complete lead training.
Alignment
The next call will be Tuesday, 10 December 2002, at 1:00 CDT in WH-2NE, Snake Pit.