|
15 April 2003 |
Location |
Phone Number |
Access Code |
|
WH-2 NE |
865-673-6703 |
334823 |
Progress Updates and Issues
- Upstream Beamline
- Targets
- TPC - Time Projection Chamber
- Magnets
- CKOV - Cerenkov
- DC - Chambers
- TOF - Time of Flight
- RICH - Ring Imaging Cerenkov
- ECAL - EM Calorimeter
- NCAL - Hadron Calorimeter
- Gas Systems
- DAQ - Data Acquisition
- MC - Monte Carlo
- Installation
- MC7 - Enclosure and Counting House
- Meetings
- Project Management
Leon Beverly's meeting summaries in italics.
BEAM - Beamline
Raja:
We had a MIPP beam line meeting today and I raised the question of beam fluxes permitted in MC7. The answer from Chuck Brown can be summarized as follows.
During beam tuning, we will need to restrict the flux into MC7 to be < 106 particles per spill for radiation safety reasons. There is no way they can bring 1011 into the enclosure with its existing state of shielding. So the old scheme of tunign the beam by bringing 1011 into MC7 is no longer valid.
So even during beam tuning, the calorimeter would be OK in its installed position.
Secondary beam will be tuned using MIPP beam chambers and not using SWICS for the same reason. So it is in MIPP's interest to get the beamline instrumentation and DAQ for the beam chambers working early on.
At [last Thursday's] meeting it was decided to have the MIPP primary copper target be a rectangular rod of 20 cm length and cross section 0.5 cm square. The primary beam spot is expected to be collimated and to be ~ rectangular of 0.4cm square on target. Mikhail Kostin made a first pass at shielding. Chuck pointed out that the shielding was too good by ~ a factor 100, so Kostin is going to try and reduce the iron in the shielding, which makes it easier to install.
Raja reserving space for beam scintillators at either end of the BCKOVs.
UBL - Upstream Beamline Detectors
BCKOV
Terry Tope:
Attached is a req for a pressure transducer [Transmitter, Barton AII Absolute, FKAG-03V4-ADCYYAA, 0-14.7 PSIA calibration range, 4-20 mA output] for each beam ckov. I could not find anything on site that I am comfortable using to calculate the density in the beam ckov. They are +/- 0.1% over the calibrated range of 14.7 psia. We have several pressure instruments from this company on site and they are easy to calibrate and the company supports us quite well. I think we should go ahead and try and purchase these. For my test I have a cheaper one, but I would not try and do physics with it.
I made a plot of the instrumentation error for the bckovs (attached .pdf). The blue line is the transducer I made the req for. The red line is an additional transducer that could be purchased for the lowest absolute pressures to improve density calculation accuracy.
The points I want to make are:
- RTD error is insignifcant compared to pressure transducer error.
- The pressure transducer error for the 0-14.7 psia instrument I want to buy could lead to a density error of 1% at 1.742 psia.
- Adding a second 0-2.321 pressure transducer would delay the possible 1% density calculation error until 0.545 psia.
So the question is then, is the error of the blue curve acceptable? If its not, then the only solution I see is to buy a 2nd transducer. Food for thought.
Photos of the beam ckov test vessel [are posted on BCKOV page]. Its pretty much done and ready to go. It has 6 RTD temperature elements and fast/slow gas fill and fast/slow vacuum capability. It should gives us an idea if this idea is what we really want. So the sooner we get the APACS modules ordered the better. I'm still working on the programming for the ckov and the gas mixing. This week I need to go over where I want to place the various gas racks with Leon.
Pipe length getting longer with new beam line design; Opal/Smith to update MC7 floor plan drawing.
TGTW - Target Wheel
Peter Barnes:
A few questions/comments:
- There is some value in minimizing the mass around the targets. It appears from [Eric Erdos'] sketch that the target wheel support plate is solid, with just a hole for the beam. Can this plate be opened up to reduce the mass around the target? Perhaps:
__ _
| \ / |
| \ / |
| \ / |
| \ / |
| \ / |
| -------- |
| |
| |
| |
----------------------
- How is the upstream/downstream limit of the target wheel set? With set-screw bushings on the upstream ends of the rods?
- How do we change out target wheels? Remove the whole assembly? Pull the wheel upstream, then reach in from the side into the old laser bay? Are we just changing targets, not target wheels?
- We need to mount a veto scintillator somewhere upstream of the target. An obvious place is to mount it off the upstream face of the optics table, or from your outer window flange, if this doesn't interfere with 3 above. Can we add a hole pattern to one side for this future mounting purpose? (The veto scintillator will be a doughnut, to veto beam halo particles. It needs to be within ~1 m of the target.)
CTGT - Cryogenic Targets
NTGT - NuMI (MINOS) Target
Peter Barnes:
Have a lead on hermetic, isolated ground, front bulkhead mount BNCs. If this fails, I will add gaskets and epoxy to seal the existing connectors.
Jim has design sketches for cam followers and cart lockdown. MAB starting fabrication.
ZipTrack
JGG - Jolly Green Giant
Ready to operate.
Rosie
Plan to connect DC leads Thursday. PS checkout Friday. Will request pORC prior to Holger's 30 minute test of magnet fringe field for TOF.
Needs to be anchored to steel box. DS end of steel box probably cannot be cut out, so DC2 (or its stand) will have to go up and over. Rather than setting up their own PMT test stand, one may be available at Lab 6.
DC1-4 (E690 Chambers)
Dave Northacker:
As of 3:30 pm today [Fri 11 April] we have been running argon-ethane (50/50) in the test chamber currently in use at lab 6. It should be fully purged by Monday afternoon (at our current flow rate providing about 1.5 volume changes per day). The change from argon-isobutane has been approved by the appropriate lab personnel.
DC1
Next on test stand.
DC2
One anode and one cathode plane left to install. Close up on Wednesday and check for shorts. Seal up and begin HV training next week.
DC3
Next to clean.
DC4
Move to MC7 May 1.
Discriminator towers have returned from IIT to Fermilab. Pierrick will contact Stan Orr w/CC to Win Baker to discuss LVHI safety reviews
140 of the 13 pair cables (preAmp -> Discriminator) have been tested, and 3% failed.
DC5 & DC6 (Iowa Chambers)
Discussion of possible test mounting/real mounting/testing sequences.
Working on mounting support options with Fermilab unistrut. First shipment of 10 x 10 cm2 scintillator due next week. USC is finding crosstalk with some of their discriminators, planning to get some from prep and check those. Looking at building 2 small counters for T0 and beam definition/trigger, one close to target and one elsewhere.
LED pulse shape and height fixed. Putting DS cover on 3/16.
Mike Longo:
I finally have a new account set up for expenses related to the MIPP calorimeters. My understanding of the situation is as follows:
- The EMCAL and HCAL will have separate bases.
- The base for the EMCAL will be a simple platform on casters that roll on the standard MIPP track. For longitudinal stability, it will probably need to extend downstream a short distance on either side of the HCAL. No specific horizontal or height adjustments will be provided, other than shimming to allow for some height adjustment.
- The Michigan group will build the unistrut frame to support the EMCAL. It will sit on the base [we] are designing.
- The HCAL will move on separate rails or metal plates.
- The main concern for the HCAL base is to allow for access to the phototubes under the calorimeter. Some modifications to the existing stand would be desirable to improve access.
We may want to make some provisions to roll both calorimeters off to the side to reduce radiation exposure while tuning the beam. This is still under discussion.
Awaiting final lead wipe of MC8 by the ES&H group. Also awaiting design of support stand.
See Beam discussion for resolution of beam tuning intensity question.Support stand design does not have to accommodate moving HCAL off beamline during beam tune up. Jim K will decide by Tuesday, 3/22 who will be assigned to design of support stand. The light tight box will be finished this week.
Alignment
Finalizing beam sheet. Also will set beam height in MC7 at 81.466" and propagating that beam height back to MC5.
The next call will be Tuesday, 22 April 2003, at 1:00 PM CDT in WH-2NE, Snake Pit.