Date |
Summary |
|
PPD MD to assist beam mechanical design; CKOV PMT testing plan in Lab 5; MC8 lead free after ECAL assembly. |
|
|
Low intensity tuning plan; BCKOV gas test stand; TGT wheel questions; ECAL stand. |
|
|
Target wheel changer support sketch; target list; magnet PS work completed; RICH front end board tests; NCAL dose discussion. |
|
|
BSHEET program revived; BCKOV schedule; CKOV mirrors installed; TOF MCS study corrected and improved; ECAL planes built; offline event looper example. |
|
|
Updated particle flux tables; DC detailed schedule; TOF MCS study; NCAL electronics. |
|
|
First resurrected beams group meeting on Thursday; BCKOV PMT order ready; DC discriminator tester ready; TOF MCS issue; RICH front end boards starting to arrive. |
|
|
Thin target wheel changer update; position TPC cart using cams; started producing ECAL planes. |
|
|
PAC presentation 28 March; simplified BCKOV gas system; beam size may be too large for target; TPC cart has horizontal play. |
|
|
Beam chamber racks in place; magnet PS installation; DC electonics Xtalk located to preamps; air cool RMH racks; TOF stand concepts. |
|
|
Alternate beamline proposal; BCKOV parts; TPC clean room ready; DC3456 stands in fabrication; APACS gas monitoring; EMCAL prototype complete. |
|
|
Improved dispersion from reversing quad polarities; BCKOV coating decision; TPC clean room done; Rosie 8 zoil ZipTrack done; DC1 repairs done; ECAL 1st prototype plane done; NCAL readout description; revised rack and module lists; network installation complete. |
|
|
Improved upstream quad scheme; Rosie ziptrack to start; repairing last DC1 plane; TOF thickness studies nearly complete. |
|
|
UVA not able to work on beam chambers; BCKOVs taken to MAB for work; first pass at BCKOV gas system design; TPC stand parts in hand, install after shutdown; JGG ZipTrack complete; ECAL lead HA signed. |
|
|
Progress on way upstream beam hardware to MTest; BCKOV 7 mr mirror hole done; small Rosie LCW leak; DC5 & DC6 PO ready; gas system one-line drawings. |
|
|
TPC cart and rails delivered, stand next week; JGG ZipTrack started; next meeting 1/7/03. |
|
|
7 mr BCKOV mirror out for hole; Ziptrack setup on JGG this week; JGG powered to full field!; Rosie LCW hoses in; DC electronics testing started. |
|
|
TPC stand delivery 4 weeks; magnet pROC walk-through 12/9; DC |
|
|
Beamline design study; TPC cart/rails/stands ordered; magnet LCW underway. |
|
|
First BCKOV mirror ready to be resurfaced; some dead TPC sticks repaired; DC356 tie-downs; ECAL lead HA in progress; MC7 survey network complete. |
|
|
Beams work has support of BD Head; new TPC CLK/TRG modules; magnet connections progress; extensive Iowa chamber discussion. |
|
|
Beams work on hold pending FY03 funding; magnet headers proceeding; Michigan ordering EMCAL lead sheets. |
|
|
Collaboration mtg schedule; ZipTrack probe calibration; EMCal lead located; Freon 13B1 venting not allowed. |
|
|
Hall probe discussion; JGG task list; DC testing task list; transfer frame aligned. |
|
|
Welcome Holger!; beamline work stopped; TPC stand quotes; Ziptrack moves!; DC3 stand engineering done; RICH equipment list; ECAL concepts. |
|
|
Beamline work list; aperture studies; Ziptrack progress notes; Iowa DC stand drawings started; RICH mirrors aligned; gas systems info and questions. |
|
|
TPC stand and cart out for bids; TPC stick repair progress; ZipTrack runs intermittently; DC transfer frame parts in hand; RICH mirror alignment started. |
|
|
MC6 lead contamination removed; TPC stand and cart drawings ready for check; magnet LCW from MS6; Ziptrack recovery progress; ECAL design concept. |
|
|
Beamline LCW discussion; TPC GG design; DC cableway design complete. |
|
|
Ziptrack resurrection plan; DC cableway/manifold design complete. |
|
|
Lead contamination in target pile; TPC stand drawings in final check; magnets being painted; DC2 stand delivered; starting CKOV cart installation; comprehensive TOF report; MC7 roof and insulation complete. |
|
|
TPC stand drawings checked; started resurrecting ZIPTrack; CKOV cart and rails delivered; VME PPC boards ordered; DAQ chain test setup at Livermore; MC7 roll up doors installed. |
|
|
Interference resolved by shortening BCKOV 3'; ROSIE welding complete. |
|
|
Possible interference between MC6Q5 and BC1; TPC stick repairs discovering other problems; magnet supplies will be in ME6 area of MDB; RICH VME boards being stuffed. |
|
|
Complete MC5-6-7 drawing; TPC Stick test stand operational; first sticks delivered to Bob Jones; CKOV and DC2 stands in fabrication; RICH VME boards delivered; MC7 building installation started. |
|
|
Beam sheet released; TPC Stick test stand problems; DC noise progress; network design started. |
|
|
TPC stand redesign complete; setting up TPC Stick test stand in MC7; new CKOV/DC2 quotes due 7/15; C4F10 venting permissible but discouraged; TOF progress details; testing RICH HV supplies. |
|
|
Modify TPC stand for LH2 target; need 2nd CKOV/DC2 stand quote; RICH controller board PO ready. |
|
|
TPC stand design progress; ROSIE forces; CKOV/DC2 drawings complete; RICH stands and rails arrived; east rail installed. |
|
|
Standing beam meeting; ROSIE welding; full DC testing begun; TOF hardware tests; RICH tracks arrived. |
|
|
"Standard" motor controls for BCKOV; magnet assembly complete; CKOV, DC2 Stand dwgs ready for signature; DC adapters arrived; RICH tank to move this week; |
|
|
Target pile open to steel shielding; TPC stand concept; JGG assembled; ROSIE in progress; CKOV stand drawings in final revision; beam height (based on JGG steel) set at 81.225", to be checked after June shutdown. |
|
|
Lost target pile rigging crew; BEAM CKOV pipe prep details; magnet assembly started 5/21; first DC adapter boards next week; JGG base sets beam at 81 1/2". |
|
|
Beam CKOV pipe scavenged from MW6; DC2 stand dwgs 70% complete. (Light meeting due to collaboration meeting on Saturdday.) |
|
|
Target pile top layer 30% removed; LBNL TPC archives being transferred to LLNL; temporary MC7 wall complete; CKOV cart engineering done; updated RICH electronics plan; Linux booted on PPC VME board. |
|
|
MC6 target pile opened!; retrieved TPC docs and chips from LBL; CKOV stand design progressing; DC tasks; TOF component testing. |
|
|
Start opening MC6 pile next week; BCKOV mirror hole sizes; TPC gating grid started; Rosie slab done, start opening roof next week; CKOV stand design complete. |
|
|
Preliminary beam sheet; TPC gating grid; Rosie pad pour next week; RICH and magnet scheduling discussion. |
|
|
Open MC5&6 piles starting 4/22/02; testing Linux VME boot; JGG force on CKOV stand is negligble; TOF component testing progress; floor survey complete: tentatively raise beam elevation by 0.5" to 81". |
|
|
Magnet ass'y procedures ready for signature; MC7 floor survey preliminary results; TOF and CKOV stand fringe fields for next week; RICH stand drawings set distribution. |
|
|
Consider moving primary target DS; target list proposal; floor survey complete, data available soon. |
|
|
CKOV prelim design complete, including support for Chambers 1 & 2; RICH stand revised; floor elevation and magnet positions to be surveyed. |
|
|
Revised JGG ass'y procedure, buy support stands, pipe for Beam CKOV, funnel PO's through LLNL to save on FNAL overhead. |
|
|
Rosie slab designed, RICH elevation, fringe field analysis for TOF, MC7 west side door. |
|
|
Rosie on concrete slab, TPC decabling 2/16, move 2/28, floor survey 3/1, engineering mtg 2/15. |
|
|
Installation Conference Call: |
|
|
Need support stand timelines, need Rosy pad estimate, new locations with no interferences, TPC move from MTest, MC7 floor elevation survey, systems expert meeting 15 Feb, new dial in access to this meeting. |
|
|
Possible change to installation sequence, Rosie base, resolving component locations, TPC adjustment. |
|
|
Magnet settling, Rosie elevation. |
|
|
Resolving interferences, magnet bases to be shimmed then grouted, cost tracking and reporting procedure, systems contacts. |
|
|
Need to resolve some interferences, magnet installation prep, counting house work. |
|
|
MOU and SOW near completion, component locations and contacts, counting house. |
|
|
Rosie coil water flow results. |
|
|
Magnet installation issues. |
|
|
Cost tracking by WBS, MOU progress. |
|
|
Rosy and JGG coil flushing, RICH stands designed, TPC nearing test, Craig Moore temporary Beams contact. |
|
|
12 October 2001 |
Thornton Murphy passed away Friday, October 12, 2001. |
|
Rosy coil dented, will flow test Rosy and JGG, US roof and door to go next week. |
|
|
Slab poured last week, US roof and door schedule 11 Oct, shoring complete and inspected, JGG coil back, flushed, other coils to be flushed. |
|
|
Shoring fab complete, installation 30%, finish 9/28, US roof in procurement, DS roof req needs Cooper signature, ICO discussion. |
|
|
Shoring fab at 2 sections/day (14 total), installation started, gas system engineers assigned, no extraction studies before 10/8/01 shutdown, Rosy assy. dwgs nearly complete, RICH undercarriage design started. |
|
|
FESS approved shoring, fab starts today, roof and door requisition submitted, momentum resolution study complete. |
|
|
Awaiting FESS approval of shoring, MC7 slab and steel shoring on order, rollup door moving upstream, coil repairs progressing. |
|
|
MB shoring requires 2 rows of supports, Ansly cables moving to MB8, JGG and ROSY install in FY02, modify LLNL ICO. |
|
|
MB shoring plan and schedule, MC7 roof mods, BM109s removed, JGG coil progressing for mid-Sept delivery, Murphy note on raising the beam elevation. |
|
|
Continuous slab under JGG & ROSY, insufficient rebar in MC7 floor needs evaluation; JGG coil being unwound, retaped, rewound, costing 2 weeks; transfer hall magnets aligned, more work during October shutdown. |
|
|
Steel support concept for MB, water circulation in TPC with no leaks, DAQ work started in earnest. |
|
|
Soil loading issue requires slab, raises beam to 80.5"; JGG repair progressing, assessing Rosy coil damage. |
|
|
18 July 2001 |
No minutes. |
|
1/3 of Ansly cables removed, 1/3 to be removed, 1/3 to be scrapped; JGG coil damage found, looks repairable; use Longo's Hyper-CP calorimeter; adding DS steel and calorimeter work to ICO. |
|
|
Bob Woods assigned to MB structural assessment, Rich Schmitt for gas systems, people unvailable due to Snowmass. |
|
|
Need structural assessment of MB for magnets, initiating BM109 removal, JGG coil out for repair, radiation shielding questions. |