Task Description |
Completed |
|
|---|---|---|
|
5.1 |
Ground gas rack and bottle rack. |
29 October 2001 |
|
5.2 |
Install smoke detectors over TPC stick card bays. |
2 November 2001 |
|
5.3 |
Run FIRUS cable to tie smoke detectors to FNAL FIRUS system. |
8 Novemeber 2001 |
|
5.4 |
Tie in to FIRUS. |
|
|
Task Description |
Completed |
|
|---|---|---|
|
4.1 |
Modify gas rack per Tope design. |
29 October 2001 |
|
4.2 |
Install bottle rack adjacent to TPC. |
17 October 2001 |
|
4.3 |
Locate P10 bottles, and move to MTest. |
26 October 2001 |
|
Task Description |
Completed |
|
|---|---|---|
|
3.1 |
Move gas rack to area adjacent to clean room. |
25 September 2001 |
|
3.2 |
Add ground bus bar to rear of VME racks. Tie to earth ground with 0 or 1 AWG wire. (This is possible, right? We don't have to run back to the transformer for this, do we?) |
Deferred |
|
3.3 |
Put DC racks on isolated AC ground, as large gage as possible (2 or 1 AWG preferred); connect to VME racks AC ground. |
Deferred |
|
3.4 |
Put HV racks on isolated AC ground, as large gage as possible (2 or 1 AWG preferred); connect to VME racks AC ground. |
Deferred |
|
Adding isolated grounds to the racks is a significant amount of work. Let's wait until we see we need this. We can plan to do this right in MC6. |
||
|
3.5 |
Ground TPC to HV racks using 2 or 1 AWG insulated ground wire. Follow the HV cable path. |
17 October 2001 |
|
3.6 |
Add cable reliefs to cable trays, especially for fibers. |
28 August 2001 |
|
3.7 |
Complete water interlock by connecting wire pair through chiller relay and flow meter relay. |
25 September 2001 |
|
3.8 |
Build assorted 10 pin ribbon cables with IDC connectors:
|
28 August 2001 |
|
3.9 |
Configure CLK/TRG NIM module to use +6V from NIM bin. (This is the module I left on Leon's chair, marked for John Bell.) |
28 August 2001 |
|
3.10 |
Repair/replace AC cords on assorted rack fans and NIM crates in HV rack. |
28 August 2001 |
|
3.11 |
Beg/borrow/steal/buy a DVM to live in MT. We'll keep it locked up when not in use. |
|
|
3.12 |
Supply an alcohol wash bottle (with alcohol!). |
28 August 2001 |
|
3.13 |
Clean all on-board fiber connectors (2 x 128). Also open, clean , and remate the connections in the middle of the orange bundle. These are in the cable tray above the gate next to the DC racks. Finally, retest the fibers that Jennifer identified as "bad". (Use a good fiber as the return and subtract its loss.) |
Deferred |
|
It may be better to replace ALL the fibers with new jacketed multi-fiber cables, from Black Box, for example (~$5K for 4 x 36 fiber x 125' cables). |
||
|
Task Description |
Completed |
|
|---|---|---|
|
Mechanical |
||
|
2.1 |
Finish water system plumbing. |
18 July 2001 |
|
2.2 |
Replace 2 missing water distribution (blue) hoses on TPC. |
1 July 2001 |
|
2.3 |
Put 3 Gating Grid Power Supplies on rack slides in DC racks. |
Cancelled |
|
Along the sides of the chassis' there are lots of screws with the heads on the outside of the chassis. Therefore the sides cannot fit flush. According to John, it is a major overhaul to eliminate the screw heads. Also, there is a problem getting the slide location to fit properly. There is a tight tolerance getting the chassis slides to align properly while keeping the front panels heights spacing correct. John can tells you about it when you return. Can we do without installing the slides? |
||
|
2.4 |
Replace air filters on 4 blowers in DC racks. Filters are in the bottom of one of the racks. |
Filters on order. |
|
2.5 |
Could we have a full height cabinet, with a lock, for storing parts and tools? |
1 June 2001 |
|
2.6 |
Repair broken panel screws on 3 power supply modules with black tape flags on handles. |
1 July 2001 |
|
AC Electrical |
||
|
2.7 |
String chiller AC cord over to outlet. We need to keep the floor clear so we can get gas bottles in to and out of the corner. |
1 July 2001 |
|
2.8 |
Move VME crates to FNAL yellow double rack, on dolly. This pair needs four separate circuits. |
1 July 2001 |
|
2.9 |
Move other components to FNAL yellow double rack, on dolly. |
1 July 2001 |
|
DC Electrical |
||
|
2.10 |
Build 1 24V power cable, using the black cord as a model. |
1 July 2001 |
|
2.11 |
Build 3 24V control cables, using the gray cord as a model. |
1 July 2001 |
|
2.12 |
Build 1 24V Water Interlock cable:
|
30 July 2001 |
|
2.13 |
Build 1 24V Master Interlock Permit:
|
30 July 2001 |
|
2.14 |
Build 1 24V Master Interlock Remote cable:
|
30 July 2001 |
|
2.15 |
Check/replace airflow sensors in:
|
30 July 2001 |
|
2.16 |
Run the rest of the DC power ribbon cables following my model:
In all areas, keep the cables stacked in order. They are not labeled yet . . . |
1 July 2001 |
|
HV Electrical |
||
|
2.17 |
Adjust zero/full scale, and repair as needed, "EOS TPC Anode Current Monitor", blue panel, in HV rack. I'm tracking down a schematic. |
Need schematic. |
|
2.18 |
Find/build 18 SHV cables, 100 feet long. |
1 July 2001 |
|
2.19 |
Find/build 18 SHV cables, 6 feet long. |
1 July 2001 |
|
2.20 |
Find/build 1 cable for Bertan 225 HV PS:
|
1 July 200 |
|
Task Description |
Completed |
|
|---|---|---|
|
AC Power |
||
|
1.1 |
Connect chiller to AC |
26 Apr 2001 |
|
1.2 |
Add third circuit to center double electronics (blue) rack. This is the most populated pair. When I turned on all the crates, one breaker (#12?) tripped after a few minutes. Do you plan to replace these with FNAL racks? Would be nice, if racks are easy to come by, but not so nice since you've got the AC power installed. |
1 July 2001 |
|
DC Power |
||
|
1.3 |
Finish checking the DC supplies. |
1 July 2001 |
|
1.4 |
Remount them in FNAL yellow racks. |
1 July 2001 |
|
Chiller |
||
|
1.5 |
Refill and turn on chiller. Please send me the name of your person who refurbished it; I'd like to meet them and have them show me what is there, how it works, what they did . . . |
30 July 2001 |
|
Cary Kendziora, who resides @ PAB |
||
|
1.6 |
Manifold brackets being made in MAB under Otto. Follow up so they are done by my visit. |
26 Apr 2001 |
|
1.7 |
Identify fittings, etc for new cross manifold. |
30 July 2001 |
|
Cable Trays |
||
|
1.8 |
Install cable trays, both inside and outside the clean room. |
1 July 2001 |
Template:
|
Task Description |
Completed |
|
|---|---|---|
|
n.m |
Description |
DD Month YYYY |